Russellville Public Works - North Phoenix Expansion Project
Click on a month to see pictures of the work completed during that time.
September 2011
October 2011
November 2011
December 2011
February 2012
March 2012
September, 2011
Initial clearing of route
October, 2011
Building up roadway and drainage
November, 2011
Bridge footings placed and major drainage completed
December, 2011
30' Box culvert installed. Road leveled & gravel placed.
February, 2012
Major drainage work completed.
March, 2012
Bridge completed. Work on Glenwood & Reasoner intersection.